Modular Scaffold for shoring – Mock up and Training for KVMRT package V207

Scaffold Shoring

Dscaff training program using our SAS modular scaffolding for a shoring application at our Klang warehouse. 10 qualified scaffolders using SAS for the first time erected 360 in 3 hours ( 12 per man / hour ).

The 1.5m bay configuration shown: Dscaff SAS has a Safe Working Load of 64 kNper leg ( AS/NZD and EN standards ). This capacity can be increased to 88Kn when using 1m lifts, ensuring less material and reduced labour time on your project.